Manufacturing

We look for the highest quality and standards in all materials we use, therefore apply tensile and compression tests to all our members (such as tubes, nodes, nuts and cones) in every phase of production and prepare quality certificates starting from the very first raw material assurance to the final installation stage at our factory in Şekerpınar which is built over an area of 10.000 m², has an annual production capacity of 500.000 m² and equipped with the highest technology and equipment. We have built implemented in our facilities a surface treatment process and a paint oven automation in the sector in order to achieve the highest corrosion protection. We have developed new techniques to protect the Space Frame members from the inner surfaces which extended the product life against corrosion remarkably.

700.000 pieces of Space Frame elements are produced with automated methods by 6 gas metal arc welding (GMAW) units annually. The steel workshop, with an annual capacity of 2.800 tones produces every types of purlins, purlin stools, steel columns and beams in house.

Our 5-Axis Vertical Machining CNC Centers with double decked preloading capability can produce 320.000 pieces of nodes from raw material to finished elements within diameters ranging from 60 mm – 240 mm annually.

Our computer controlled facility of surface treatment and phosphating is unique in Turkey with the capabilities of oil removal, dust removal, activation, phosphating, pacification and rinsing. The facility works with 10 baths with a 7 tones of liquid capacity each which gets the structural members clean and resistant to corrosion and prepares the their inner and outer surfaces for painting.

Fully computerized electrostatic paint oven can automatically paint pipes of 3.60 m length by axial rotation with 2 robots each having 4 spray guns. The oven can also paint purlins and steel construction members up to a length of 7.20 m.

  • Powder Coating
  • Nodes
  • Bars & Cones (Conical Tips)
  • Bolts, Nuts and Pins
  • Purlin Fixing Elements and Purlins
  • Protection Against Corrosion
Powder Coating

The surface of each part is entirely painted by a thin layer of 80 microns, smooth and bright pellicle. Then the sprayed parts are transferred into ovens at 200°C where they are kept until the required hardness of the powder coat is reached. The electrostatic powder coat has a longer life than the regular wet coatings or the coatings on-site because they are more resistent to strokes, temperatures ranging between ( –35°C) - ( +280°C), UV rays and erosion. The surface is smooth and without any blisters, flakes or stains.

The parts which can not be powder coated, can be coated with wet paint method with the approval of the principal. In this case, the wet paint can be applied in several layers until the coat thickness reaches 30 - 40 microns. Colors are chosen from the RAL catalogue and the finishing can be in dull, semi dull, bright or semi bright tones.

Nuts are hot-dip galvanised at 50 microns and the powder coat is applied on top. Nodes are electrogalvanised at 20 microns and the powder coat is applied on top. Bolts are electrogalvanised at 20 microns.

Nodes
The joint nodes of the bar members are spherical in shape and manufactured of C45 steel by hot forging method which comply to the DIN EN 10083-1/-2/-3 norms. The number and the angles of the holes to be bored and threaded in each node are calculated separately for each project. The total number of holes per node shall be less then 18 holes.
Bars & Cones (Conical Tips)
Bars are made of circular hollow section pipes with conical tips welded at each end. The function of the conical tips is to transmit the tensile and compressive forces. The bars and conical tips are produced of Steel grade ST 33 (S235), ST 44 (S275) or ST 52 (S355) complying with material norms DIN EN 17 100. Gas metal arc welding method is used for welding the conical tips to the pipes and the method complies with DIN 4100 and DIN 4115 norms. The bars are not completely enclosed and they have a functional hole at one end. The materials used in the projects are specified by appropriate material symbols.
Bolts, Nuts and Pins

The Bolts are functioning by means of conical tips welded at the pipe end. Before welding of the conical tip, the head of the bolt is inserted in the conical tip so that the head of the bolt remains inside of the pipe and the treaded part outside. Therefore, the conical tip lets the bolt rotate freely in every direction. The bolt had also a transversal orifice for pinning.

Nut is the hexagonal hollow section between the conical tip and the node element. The nut has two long orifices, one on each of its two symmetrical sides. The nut is mounted to the bolt, the pin is fixed into the bolts in such a way that its free ends are captured in the nut orifices and by the free rotation of these ends, the pins help the fixation of the bars to the nodes. The bolts are manufactured in conformity to DIN 267 requirements. ISO compiant threading processs is performed according to DIN 13.

Purlin Fixing Elements and Purlins

Purlin Fixing Elements
They are used to adjust the roof inclination and are fixed to the top holes drilled into the top cord nodes. These parts can be manufactured of pipe, of corner profile or a different section profile, depending on their functional requirements. Their dimension depends on the roof inclination.

Purlins
They are made of steel grade ST37 and their section can be C, U, Z or square hollow section profile, depending on the type of roof cladding.

Protection Against Corrosion
The corrosion protection is provided by the method of hot dip galvanization that is applied to Space Frame elements in conformity to EN ISO 1461. The life time of the hot dip galvanisation is between 10 - 20 years and this period can be extended considerably by the application of protection materials on the galvanised surface. However, in some cases, the hot dip galvanisation and powder coating methods can not be applied to certain components such as purlins, columns, supports etc. In this case, the hot dip galvanisation method is replaced by the spraying and powder coating.